Quotations have been obtained for making up all the remaining dirt roads on the park to Tarmac.
One is for 6 Euro per square metre, and the other is for 8 Euro per square metre. Based on these figures it is estimated the total cost will be in the region of 100,000 Euro. In order to minimise the possibility of flooding owners properties, the existing roads will be dug out, new hardcore laid with the tarmac on top to finish at or below the present level.

Various options are being considered on ways to raise the money for this project, and a separate savings bank account will be set up for this purpose. It is hoped a firm set of proposals will be available to put before all owners at the AGM in September.